How to Prepare CDM Information for Your Project

How to Prepare CDM Information for Your Project

A construction project can lose control of risk long before work starts on site. Missing surveys, unclear residual hazards, incomplete service records and late design decisions all create conditions in which contractors are forced to make assumptions. Knowing how to prepare CDM information properly gives dutyholders the evidence needed to plan, design and deliver work in accordance with the Construction (Design and Management) Regulations 2015.

CDM information is not one document produced at the end of a project. It is a managed set of proportionate, project-specific information that develops from the client brief through design, construction, handover and future maintenance. Its quality directly affects tender accuracy, the construction phase plan, RAMS, site controls and the health and safety file.

What CDM information must achieve

Under CDM 2015, the client must make suitable arrangements for managing a project, including allocating sufficient time and resources. The Principal Designer has a central role in planning, managing, monitoring and coordinating pre-construction health and safety matters where more than one contractor is involved. Designers and contractors must then use and contribute relevant information within their own duties.

The objective is not to generate excessive paperwork. Information should identify the significant hazards that are likely to affect design choices, construction methods, future use, cleaning, maintenance, alteration and demolition. It must be clear enough for those receiving it to act on, rather than merely acknowledge it.

The information required will depend on the project. A roof replacement at an occupied school, for example, may require asbestos information, fragile roof surveys, fire strategy considerations, access constraints, safeguarding arrangements, structural details and work-at-height planning. A civils scheme may instead depend on utility searches, PAS 128 survey data, HSG47 controls, ground investigation findings, contamination data, drainage records and temporary works interfaces.

How to prepare CDM information before construction

The most effective approach begins before appointing the design team or contractor. Start by defining the project scope, its boundaries, operational constraints and intended outcomes. A vague brief produces vague risk information and makes later changes more likely.

Establish the dutyholders and information route

Confirm who is acting as client, Principal Designer, Principal Contractor, designers and contractors. On smaller projects, one organisation may undertake more than one role, but the duties still apply. The client should establish how information will be requested, reviewed, issued, updated and retained.

A clear information schedule is useful. It should identify each required survey, report, drawing, specification, record owner, due date and recipient. This prevents critical information being held in separate inboxes or released only after the design has progressed.

For notifiable projects, the client must ensure an F10 notification is submitted to the HSE. Notification is not a substitute for suitable management arrangements or competent appointments.

Gather existing records and verify their reliability

Collect available records early, including previous health and safety files, operation and maintenance manuals, record drawings, fire risk assessments, asbestos registers, structural reports, utility information, environmental reports and maintenance histories. Do not assume that historic information is accurate simply because it exists.

Consider its age, source, coverage and limitations. A utility plan may indicate known apparatus but not confirm its precise position. An asbestos survey may not cover areas that will be disturbed. Record drawings may differ materially from the installed building. These limitations should be stated so that designers and contractors can specify further investigation or appropriate controls.

Where work affects existing buildings, an intrusive refurbishment or demolition asbestos survey will often be required before disturbance. Similarly, structural alterations may need a targeted structural survey, and excavation works may require ground investigation and utility detection. The purpose is to reduce uncertainty before construction methods are fixed.

Produce proportionate pre-construction information

Pre-construction information, commonly referred to as PCI, is the core CDM information issued to designers and contractors before construction begins. It should be assembled by the client, with support from the Principal Designer where appointed, and kept live as the project develops.

Good PCI normally addresses the project description, client requirements, site location and access, programme constraints, existing site hazards, relevant surveys, planning and building-control constraints, known design assumptions, adjacent activities and emergency arrangements. It should also identify residual risks arising from the design that cannot be eliminated or reduced further through design development.

The PCI should not duplicate every available report without explanation. A contractor needs to know what is relevant, where the supporting evidence sits and what action is expected. For example, rather than attaching an extensive environmental report without context, identify contamination zones, material handling requirements, disposal constraints and any monitoring requirements that affect the works.

Coordinate design risk management

Design risk management is where CDM information becomes operational. Designers must eliminate foreseeable risks so far as reasonably practicable, then reduce or control those that remain. The Principal Designer should coordinate this work across disciplines and ensure that design decisions are communicated to the people affected.

A design risk register can support this process when it records the hazard, affected parties, design measures considered, residual risk, required construction controls and responsibility for close-out. It should not become a generic list of site risks. Risks such as hard hats, slips and routine manual handling are ordinarily controlled by the contractor’s arrangements. The register should focus on project-specific, unusual or significant risks that need design-led action.

Typical matters requiring coordinated decisions include temporary works interfaces, lifting zones, fire compartmentation penetrations, confined spaces, work near overhead lines, live services, occupied premises, contaminated land, deep excavations and access for replacement of plant. Where fire safety is affected, the design team should also consider how alterations interact with the building’s fire strategy, compartmentation and evacuation arrangements.

Design changes must be captured. If a late specification change introduces heavier plant, altered roof loading, new maintenance access or a different installation sequence, the PCI and risk information may need updating. CDM coordination is not complete at planning stage.

Issue information for tender and construction planning

Contractors need adequate information to price, programme and plan the work safely. Releasing PCI late can lead to qualifications in tenders, unrealistic allowances, unsafe assumptions or costly variations. Allow enough time for contractors to review the information and seek clarification.

Before the construction phase starts, the Principal Contractor must prepare a construction phase plan. On a single-contractor project, the contractor has this duty. The plan should set out the site-specific arrangements for managing health and safety, including site rules, welfare, traffic management, inductions, supervision, emergency procedures, work control and coordination of subcontractors.

The plan should be informed by the PCI, surveys and design risk information, not copied from a previous project. If the project includes live utilities, occupied areas or high-risk work, the controls, permits, isolation arrangements and communication routes should be explicit.

Build the health and safety file from the start

Where a project involves more than one contractor, a health and safety file is required. The Principal Designer prepares it and ensures that it is updated throughout the project. At the end, it is handed to the client, who must retain it, keep it available and update it when necessary.

The file is for future construction, cleaning, maintenance, refurbishment and demolition work. It is not an archive of every site document. Including every inspection record, toolbox talk and daily briefing can obscure the information that future dutyholders genuinely need.

Useful content includes record drawings, locations of services and isolation points, residual structural hazards, as-built fire safety information, details of hazardous materials, access and safe maintenance arrangements, plant information, loadings, temporary works left in place, demolition considerations and relevant operating limitations. For complex assets, the information may sit within controlled asset-management systems, provided it remains accessible, intelligible and maintained.

The Principal Contractor must provide the information needed for the file as work progresses. This requires a defined handover process with subcontractors and suppliers. Leaving collation until practical completion usually results in missing certificates, unverified drawings and incomplete maintenance information.

Common failures that weaken CDM compliance

The most frequent failure is treating CDM information as an administrative deliverable rather than a decision-making tool. Other recurring issues include appointing a Principal Designer after the design is substantially fixed, issuing unverified surveys, failing to communicate design changes, using generic risk registers and accepting handover documents without checking completeness.

A proportionate but disciplined assurance process is preferable. Review information at design gateways, construction start, major change points and pre-handover. Confirm that actions have owners, evidence is available and residual risks have been transferred to the correct party.

For complex, high-risk or regulated projects, independent CDM 2015 and Principal Designer support can provide additional assurance that the information trail is complete, coordinated and defensible. Evolution Safety Solutions can support clients and project teams with CDM documentation, design risk coordination and health and safety file development.

The practical test is straightforward: could the next person planning work on the asset understand its significant hazards, locate reliable records and take safe decisions without relying on assumptions? If the answer is uncertain, the CDM information needs further work before the project moves on.